73.5 kW Scherer - Solar Project Gainesville, FL

Power Production Management designed/installed a 73.5 kW PV system across an office building and warehouse utilizing a corrugated roof attachment solution and Ejot Orkan storm washer to guarantee a watertight seal.
73.5 kW PV system over the office building and warehouse
Project Description

Power Production Management designed and installed a 73.5 kW PV system spread across an office building and warehouse. The warehouse system (54 kW) utilized IronRidge racking and the Ejot corrugated roof mounting solution with Orkan storm washers to guarantee a watertight seal. The office building solar modules were mounted on an AET Rayport B stainless steel ballasted system at a 5 degree tilt. (6) SMA Sunny Boy 7000US and (3) SMA Sunny Boy 6000US string inverters were used in a 208V 3-phase configuration. The system is installed in Gainesville Regional Utilities (GRU) territory as a net metered system.